Blog updates will typically be posted on Friday of each
week. We hope that you find the information useful. If you have any
questions, please feel free to reach out to Mike DeBennette, the project
manager, listed on the right side of the page.
Work Performed This Week, April 23rd to April 27th
·
Mill in-place and grading of the existing
asphalt pavement.
·
Mobilization of equipment and material
deliveries.
·
Connection to existing water main at the south
end of the project.
·
Water main installation from south end of the
project to culvert.
Work Anticipated to be performed next week, April 30th
to May 4th.
·
Continue with water main installation along
Blackthorn Drive from culvert to Sequoia Trail
·
Directional drilling of water main casing pipe
to be installed under the existing culvert.
As you have noticed, the amount of construction traffic has
increased since construction started this week. We appreciate your patience and
understanding as you travel along Blackthorn Drive and throughout the
neighborhood.
Two water main shut-downs also occurred last week. One
was schedule to make the connection to the existing water main on the south end
of the project, you should have received a notice from the Village Water
Department regarding this shut-down. The second was an unexpected
shut-down due to the contractor hitting a water service. We thank you for
your patience and understanding during these times.