Work Performed:
·
Poured concrete curb & gutter, sidewalks,
and driveways
·
Asphalt patched trench from culvert to southerly
project limits
·
Rough graded and clean-up of spoil behind the
curb & gutter
·
Installation and grading of topsoil in disturbed
areas, sod will not be installed until weather conditions are more favorable.
Work Anticipated to be performed, July 16th to
July 20th
·
Removing and grading base course from culvert to
Sequoia Trail
·
Paving first layer of asphalt from culvert to
Sequoia Trail
·
Complete topsoil installation and grading
·
Install in-stream controls prior to culvert
replacement
·
Remove existing culvert
·
Replace existing sanitary sewer under culvert
·
Remove abandoned water main under culvert
The roadway reconstruction will continue next week from the
culvert to Sequoia Trail. It is anticipated the first layer of asphalt
will be paved on Monday, depending on weather. The first layer of asphalt is a
significant project milestone as a smooth driving surface will be provided and
the amount of dust will be greatly reduced in the area.
Next week the contractor will also begin the culvert
replacement phase of the project. Blackthorn Drive will be closed to all
traffic within the culvert work area starting on Tuesday, July 17th.
Please plan an alternate route around this area. The gate at Sequoia Trail and
Chestnut Avenue will also be occasionally opened to allow for mobilization of
equipment and material deliveries. Any time when the gate is needed to be
opened, a representative will be on-site to open, close, and lock it once
access is no longer needed.
Thanks again to all those residents that were out of their
driveways during the concrete pouring and curing process.
Thank you in advance for altering your travel routes as the
roadway is closed to complete the culvert work.