·
Removed and graded base course from culvert to
Sequoia Trail
·
Paved first layer of asphalt pavement from
culvert to Sequoia Trail
·
Installed Road Closed signs at culvert in
preparation for culvert replacement. Unfortunately due to an unforeseen
scheduling conflict with the contractor, the work was delayed into next week.
Work Anticipated to be performed, July 23rd to
July 27th
·
Install in-stream controls prior to culvert
replacement
·
Remove existing culvert
·
Replace existing sanitary sewer under culvert
·
Remove abandoned water main under culvert
·
Depending on work progress, begin installation
of precast culvert sections.
With the first layer of asphalt pavement being completed
hopefully you are seeing a reduction in the amount of dust and easier
traveling. A majority of the topsoil is completed; however, there are some more
areas to be cleaned up, graded, and topsoil installed. Sod is still
scheduled to be performed in early fall when growing conditions are more
favorable.
We apologize for the delay in getting the culvert
replacement work started. Work is currently scheduled to begin early next
week with the hopes of getting some of the culvert re-installed prior to the
end of the week.
Thanks again for all your patience during the construction
project.