Removed existing culvert at South Navy Ditch
·
Replaced existing sanitary sewer under culvert
·
Installed new precast concrete culvert at South
Navy Ditch
Work Anticipated to be performed, July 30th to August 3rd
·
Frame and pour concrete headwalls
·
Install storm sewer that connects to new precast
concrete headwalls
·
Backfill around precast culvert
·
Depending on work progress, the roadway could be
re-opened by the end of the week.
The existing culvert was removed and replaced this past
week. Work will continue on the culvert next week with the concrete headwalls
being framed and poured along with backfilling around the culvert.
Thanks again for all your patience as you have been using
alternate routes due to the roadway closure while the culvert is being
replaced.