Work Performed Last Week, June 11th to June 15th
·
Underground utility work completed.
·
Completed
storm sewer installation
·
Installed
storm sewer services
·
Abandoned
or removed old water valves and fire hydrants.
·
Abandoned
old storm sewer mainline pipe.
Work Anticipated to be performed next week, June 18th
to June 22nd
·
Remove concrete curb & gutter, sidewalks,
and driveways on the east / south side of Blackthorn Drive from Silverwillow
Drive to Sequoia Trail. Temporary access will be provided to driveways until
concrete is poured.
·
Excavate
spoils and prepare base materials for concrete curb & gutter, sidewalks,
and driveways on west / north side of Blackthorn Drive from SIlverwillow Drive
to Sequoia Trail.
·
Pour
concrete curb & gutter, sidewalks, and driveways on west / north side of
Blackthorn Drive.
The underground utility improvement phase of the project is
now completed. The contractor has moved into the roadway rehabilitation phase.
The contractor will be removing and pouring the concrete
curb & gutter, sidewalk, and driveways on the north / west side of
Blackthorn Drive this week. Depending on weather and work progress, we are
hoping all residents without driveway access will have it restored by the
weekend. Once the concrete is poured, it
will need to cure for approximately 4 days prior to allowing vehicles to drive
over it. In cases where concrete curb
& gutter, sidewalk, and driveways are being replaced at the same home, the
period without driveway access may be extended.
Once the
driveways on the north / west side of Blackthorn Drive are replaced and access
is restored, the concrete curb & gutter, sidewalks, and driveways will be
replaced on the south / east side of Blackthorn Drive.
We do
understand the inconvenience that comes with being out of your driveway for an
extended period of time. Please understand we will do everything to reduce the
amount of time out are out of your driveways to the greatest extent
possible. Thanks again for all your
patience and understanding.