Continued with water service replacements
·
Made
connection to existing water main at Silverwillow Drive
·
Performed
sanitary sewer main line repair as required.
Work Anticipated to be performed next week, June 4th
to June 7th
·
Complete water service replacements
·
Continue to make connections to existing water
mains.
·
Complete sanitary sewer main repairs
·
Start
storm sewer installation.
Once the water main service replacements are completed later
this week, the final connections to the existing water main will be
scheduled. Residents will be notified of
the times for these water shut-downs by the Village Water Department approximately
24 hours in advance.
Thanks
again for all your patience and understanding as you deal with the dust, travel
delays, and other inconveniences of living within a construction area.