Tuesday, June 5, 2018

Water Service Replacements to be Completed. Storm Sewer to Begin

Work Performed Last Week, May 29th to June 1st
·         Continued with water service replacements
·         Made connection to existing water main at Silverwillow Drive
·         Performed sanitary sewer main line repair as required.

Work Anticipated to be performed next week, June 4th to June 7th
·         Complete water service replacements
·         Continue to make connections to existing water mains.
·         Complete sanitary sewer main repairs
·         Start storm sewer installation.

Once the water main service replacements are completed later this week, the final connections to the existing water main will be scheduled.  Residents will be notified of the times for these water shut-downs by the Village Water Department approximately 24 hours in advance.

Thanks again for all your patience and understanding as you deal with the dust, travel delays, and other inconveniences of living within a construction area.