Friday, August 31, 2018

Work Performed: 
Backfilling complete
 

Work Anticipated to be performed, September 4th to September 7th

  • Finish landscaping
  • Finish Installing retaining wall
  • Tentatively pave surface by end of next week.
 
 
Thanks again for all your patience as you have been using alternate routes due to the roadway closure while the culvert is being replaced, that portion is now complete and the road is now open to thru traffic.
We would like to wish everyone a safe and happy Labor Day weekend
 

Friday, August 24, 2018

Work Performed: 
Wing walls were backfilled
Curbs and sidewalks have been installed

 

Work Anticipated to be performed, August 27th to August 31st

  • Finish landscaping
  • Install retaining wall
  • Tentatively pave surface by end of next week.
 
 
Thanks again for all your patience as you have been using alternate routes due to the roadway closure while the culvert is being replaced, that portion is now complete and the road is now open to thru traffic.
 

Friday, August 17, 2018

Work Performed: 
Wing walls were Poured

 

Work Anticipated to be performed, August 20th to August 24th

  • Start backfilling wing walls
·        Landscaping
  • Sidewalk installation
  • Frame and pour curbs
 
 
Thanks again for all your patience as you have been using alternate routes due to the roadway closure while the culvert is being replaced.

Friday, August 3, 2018

Working towards opening the road by the end of next week


Work Performed:

·        Headwall was poured and stripped
  • Wing walls were formed

 

Work Anticipated to be performed, August 13th to August 17th

  • Pour wing walls
·        Concrete Stripping

·        Backfill around precast culvert
 
·        Install aggregate base 

·        Depending on work progress, the roadway should be re-opened prior to the start of school.

 

Thanks again for all your patience as you have been using alternate routes due to the roadway closure while the culvert is being replaced.