Work Performed: 
Wing walls were backfilled
Curbs and sidewalks have been installed

 

Work Anticipated to be performed, August 27th to August 31st

  • Finish landscaping
  • Install retaining wall
  • Tentatively pave surface by end of next week.
 
 
Thanks again for all your patience as you have been using alternate routes due to the roadway closure while the culvert is being replaced, that portion is now complete and the road is now open to thru traffic.