Friday, August 17, 2018

Work Performed: 
Wing walls were Poured

 

Work Anticipated to be performed, August 20th to August 24th

  • Start backfilling wing walls
·        Landscaping
  • Sidewalk installation
  • Frame and pour curbs
 
 
Thanks again for all your patience as you have been using alternate routes due to the roadway closure while the culvert is being replaced.