Work Performed:
·
Headwall was poured and stripped
- Wing walls were formed
Work Anticipated to be performed, August 13th
to August 17th
- Pour wing walls
·
Concrete Stripping
·
Backfill around precast culvert
·
Install aggregate base
·
Depending on work progress, the roadway should be
re-opened prior to the start of school.
Thanks again for all your patience as you have been using
alternate routes due to the roadway closure while the culvert is being
replaced.