Roadway Improvements Continue Next Week

Work Performed Last Week, June 25th to June 29th  
·         Installed concrete curb & gutter, sidewalks, and driveways along north side of Blackthorn Drive from culver to Sequoia Trail
·        Started rough landscape grading behind back of curb.
·         Rough grading of roadway to allow for access to driveways.
·         Driveway access to be restored over the weekend.

Work Anticipated to be performed next week, July 2nd to July 6th  
·         Asphalt patching of trench from culvert to southerly project limits
·         Pour concrete curb & gutter, driveways, and sidewalk on south side of Blackthorn Drive from culvert to Sequoia Trail, scheduled for Thursday after July 4th Holiday.
·         Rough grading behind curb & gutter.

Thank you to all those residents that have been out of your driveway due to the concrete work performed. 