·
Installed concrete curb & gutter, sidewalks,
and driveways along north side of Blackthorn Drive from culver to Sequoia Trail
· Started rough landscape grading behind back of curb.
·
Rough grading of roadway to allow for access to
driveways.
·
Driveway access to be restored over the weekend.
Work Anticipated to be performed next week, July 2nd
to July 6th
·
Asphalt patching of trench from culvert to
southerly project limits
·
Pour concrete curb & gutter, driveways, and
sidewalk on south side of Blackthorn Drive from culvert to Sequoia Trail,
scheduled for Thursday after July 4th Holiday.
·
Rough grading behind curb & gutter.
Thank you to all those residents that have been out of your
driveway due to the concrete work performed.
Have a safe and enjoyable July 4th Weekend.