Water main
work completed!!!
·
Completed water service replacements
·
Made
final connection between new water main and existing water main
·
Began storm sewer installation
·
Repaired
sections of damaged concrete curb & gutter.
Work Anticipated to be performed next week, June 11th
to June 15th
·
Complete storm sewer installation
·
Continue
with concrete curb & gutter and sidewalk installation once storm sewer
completed.
·
NPL
/ Nicor to be on-site to relocate gas main near large culvert
·
Comcast
potentially on-site to relate cables near large culvert
It is anticipated the underground utility (water main,
sanitary sewer, storm sewer) improvements will be completed by the end of next
week. Once that work is completed, the project will move into the roadway
improvements phase. During this time, the concrete curb & gutter and
sidewalk will be replaced where previously damaged or in poor condition. There
will be periods in which residents will not have access to their driveways for
5-7 days while the concrete is removed, poured, and allowed proper time to
cure. If a driveway is affected, each
resident will be provided with a hand-delivered letter stating when the restriction
will occur and when access will be restored.
We are
continually working with various utility companies (ComEd, Comcast, AT&T,
and Nicor) to have their facilities relocated in the area of the large culvert
replacement. Once all utilities are
relocated, the culvert will be replaced. Additional information will be
provided when this phase of the construction begins.
We
understand several residents are having issues with the various utilities due
to work performed. Although the Village does not own or maintain these
facilities, we are working to get all the issues resolved as quickly as
possible.
We appreciate your patience and understanding during the
recent water main shut-downs. No
additional water service disruptions are anticipated.