Friday, May 11, 2018

Underground Utility Improvements On-Going.

Work Performed This Week, May 7th to May 11th
·         Completed water main installation along the project site
·         Started performing necessary testing to new water main system prior to placing into service
·         Sanitary sewer service replacements as planned

Work Anticipated to be performed next week, May 14th to May 18th
·         Complete testing necessary for new water main
·         Continue with sanitary sewer service replacements
·         Begin storm sewer installation

The recent rain events have helped in controlling the amount of dust present; however, be assured we will try to minimize the amount of dust to the greatest extent possible by utilizing water, street sweepers, and chemicals as needed.  Some travel delays through the project site are to be expected, your patience in traveling to and from your home is greatly appreciated. We are committed to ensure proper travel ways are maintained to provide access. We do anticipate some potholing will occur within the trenches and gravel sections of roadway, these will be smooth out on a regular basis, but please drive carefully.

Thank you again for all your understanding as you live within the construction area.